Diagrama de Gantt - JIA Terminal Expansion Program

Jacksonville International Airport - Terminal Expansion Program

Task Name 2024 2025 2026 2027
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
JAI Terminal Expansion Program
Concourse B
Mobilization/Demolition
Sitework/Utilities
Building Piles and Foundations
Structural Steel/Decking
Building Envelope and Roof
Interior Build Out, Systems, and Finishes
Concessions and Tenant Build Out
Passenger Boarding Bridge Installation
Building Testing and Commissioning
Concourse B Ready for Use
Bypass Taxiway and Apron
Bypass Taxiway Construction
Concourse B Apron Rehabilitation and Expansion